A graphical representation of how we used Navisworks to sequence steel at the beginning of the BIM coordination process.  Upon receiving the engineer's steel model and coordinating with the project schedule's erection sequence, it took less than an hour to capture the information and create the graphic. We then distributed the image to all participants of the project (architect, engineers, trades and construction management team). Sequence 1, 2 and 3 soon became common practice when referring to steel and area locations